Capital Project Updates

February 2017: 
 
The work associated with Phase B of our capital project continues to progress.

In an effort to eliminate and/or minimize disruptions during the school day, the vast majority of work is taking place after school hours, except the construction of the new Chiz Frye Field Press Box and the renovations at the Transportation Garage.

The new press box is moving along nicely, and the steel components will soon be erected. The interior work at the Transportation Garage is nearing completion. The new bus wash is also nearing completion, and the new bus lifts are already in use.

Below is a building-by-building summary of additional work currently taking place:

Deerfield Elementary School – bathroom renovations, ceiling replacements, electrical work

Hart’s Hill Elementary School – bathroom renovations, ceiling work scheduled to begin

Marcy Elementary School – bathroom renovations

Westmoreland Road Elementary School – bathroom renovations, ceiling replacements, electrical work

Middle School – bathroom renovations

High School – bathroom renovations, ceiling replacements, electrical work, HVAC work, student locker replacement

District-wide – technology upgrades

All in-progress bathroom renovations are scheduled to be completed by early March. Once completed, additional bathroom renovations will start.

The long-term results of our capital project will enhance the learning atmosphere for our students, improve building safety and address various infrastructure-related needs.

We ask for your continued patience and support. 
 
August 2016:
 
Phase A of the Capital Project, which was approved by voters in 2014, has been completed. Work included sidewalk replacement, curb replacement and paving at all school buildings, roof work at the High School and all four elementary schools and the installation of artificial field turf at Wadas Field.  Wadas Field  

Phase B of the Capital Project began this summer, and while some work is nearing completion, work is projected to be completed in the 2017-18 school year. Below is a list of some of the major ongoing projects included in Phase B:

• Roof replacement at Hart’s Hill (nearing completion)
• Roofing work at Middle School (nearing completion)
• HVAC upgrades at High School and Middle School
• Asbestos abatement at High School, Middle School and Marcy
• Auditorium upgrades at High School and Middle School
• New student lockers at High School and Middle School
• New lobby doors and courtyard repairs at High School
• Student restroom renovations District-wide
• Central Kitchen upgrades
• Transportation Department renovations
• Press box and additional bleachers at Chiz Frye Field
• New signage at High School and Middle School
• Instructional technology improvements, such as updated SMART Classrooms and network infrastructure

Please note that work will continue at the High School throughout the school year. Administration and the contractors have taken every step to ensure that the work will not disrupt the educational process.

All of the improvements will help enhance the learning atmosphere for our students.

Thank you for your continued support ensuring our facilities meet the educational needs for students and staff. 
 
August 2015:
 
Phase A of the Capital Project, which was approved by voters in 2014, is progressing with the vast majority of work on schedule. Below, is a school by school summary of what has already been completed and what is expected to be completed in the near future. 

High School:
Completed Work
   • Paving of the lower circle and north entrance 
   • Sidewalk and curb replacement in various locations 
   • Roof repair/replacement
Nearing Completion
   • Wadas Field 
      o New field turf expected to be completed and ready for use by November

Deerfield, Marcy and Westmoreland Road Elementary Schools:  Wadas Field construction
Completed Work
   • Paving 
   • Sidewalk and curb replacement in various locations 
Nearing Completion
   • Roof replacement 

Hart’s Hill Elementary:
Completed Work
   • Paving
   • Sidewalk replacement in various locations
   • Roof replacement - Spring 2016

Phase B of the Capital Project is scheduled to start in Summer 2016 pending SED approval, and finish approximately in Fall 2016. Some of the major projects included in Phase B are: 

   • Instructional Technology improvements District-wide
   • Roofing work at Middle School
   • New lobby doors and courtyard repairs at High School
   • Student restroom renovations District-wide
   • HVAC upgrades at High School and Middle School 
   • New student lockers at High School and Middle School
   • Auditorium upgrades at High School and Middle School 
   • Central Kitchen upgrades
   • Transportation Department renovations
   • Press Box and additional bleachers at Chiz Frye Field
   • New signage at High School and Middle School
 
Below, is a photo gallery of some of the completed and ongoing work. 
 